Today the Deputy Minister of Transport, Information Technology and Communications Petar Kirov inspected the construction works on the railway line Plovdiv - Burgas.
During the inspection Deputy Minister Kirov said that the implementation of Lot 2 “Stara Zagora – Zimnitsa” is 79% complete. Eighty-four km railroad were laid and the value of the construction contract is nearly 182 million levs.
The implementation of Lot 3 “Tserkovski – Burgas” has reached 70% physical implementation and 107 km railroad were laid. The construction contract of this project amounted to nearly 163 million levs.
The contractor of the rehabilitation project of the railway line Plovdiv - Burgas is DZZD “GCF - CK 13 - Trace Railinfra Consortium”. Earlier today the Minister of Transport, Information Technology and Communications Danail Papazov opened the first Lot of the project Mihailovo - Kaloyanovets. |